About this template
Shipping the code is not the launch. Release notes, help docs, a landing page, a briefing for sales and support, a heads-up for existing customers: if any of these is missing on the day, the launch lands quietly or generates questions nobody can answer.
This template lays out the work around a launch as an editable timeline that starts from your launch date, about eight weeks from locking the scope to launch day, plus two weeks of follow-up.
Scale it to the launch. A small feature fits in half the time. A new product needs longer for messaging and enablement.
How the plan is broken down
Lock what you are launching. Scope lock is the first task, on its own. While the scope is moving, nobody can write release notes or an announcement.
Prepare to tell people, in parallel with QA. Release notes, help docs, launch assets and enablement material are written while QA runs. Starting them after the build is done is too late.
Tell people in order: the company, then customers, then everyone. An internal briefing, early notice to existing customers and a go/no-go decision come before launch day. The two weeks after are for watching support and bugs.
Why the durations are set this way
- Release notes and help docs get 20 days. Start before the screens are final and revise after QA. Written on launch day, they always miss something.
- The internal briefing comes before customer notice. If support and sales hear about it after customers do, the first questions go unanswered.
- Go/no-go sits 3 days before launch. If the answer is "no", you need time to hold the announcement.
- Two weeks after launch. Reactions and bugs cluster in the first days. The retrospective is part of the plan.
Common pitfalls
- The scope keeps moving. Every "let's add this too" pushes all the launch material back. Fix the date the scope locks.
- Support finds out on launch day. Put the briefing and the enablement material before the launch.
- Treating launch day as the end. Without looking at usage and questions, the next launch is no better.
Who finishes what before the next step starts
Launch prep usually stalls where nobody is sure whose turn it is. For each task, decide who finishes it and what "done" means before you start.
| Task | Who finishes it | Done when |
|---|---|---|
| Lock the launch scope | Product manager | What ships and what does not is listed, and engineering has agreed |
| Release notes & help docs | Product manager | The text is ready to publish and support has read it |
| Landing page, email & social assets | Marketing | Everything that goes out on launch day is ready |
| QA & final checks | Engineering | Every check has been run and the open bugs are listed |
| Internal launch briefing | Product manager | Sales and support have heard what changes and what customers will ask |
| Early notice to existing customers | Support | The notice is sent and the replies are answered |
| Go/no-go decision | Product manager and engineering | The open bugs have been reviewed and "ship" is decided |
| Launch day | Engineering | It runs in production and customers can use it |
If "done" is written as "prepare" or "align", nobody can say whether it happened. Write it as something that either happened or did not: "sent", "decided".
If QA slips by 3 days, what happens to launch day
In this plan, a delay reaches launch day along one path:
QA & final checks → Internal launch briefing → Early notice to existing customers → Go/no-go → Launch day
QA runs from day 30 to day 44. Early notice runs from day 46 to day 51, and the go/no-go decision is on day 53. That leaves 2 days of slack between the end of early notice and the decision.
If QA runs 3 days long, the briefing starts on day 47 and early notice runs from day 49 to day 54. It is still running on the day of the decision, so as planned the launch moves by a day.
Launch assets and enablement material are not on this path. They keep moving while QA runs long.
If launch day cannot move, win the time back in this order:
- Shorten early notice from 5 days to 3. Write the notice in advance, so the window only has to cover sending it and answering replies.
- Hold the internal briefing before QA ends. Explaining what changes does not need QA to be finished.
- Do not cut QA. What you skip here is found by customers.
If you cannot win it back, move the launch and tell everyone the same day. Changing the date before customers are notified costs far less than changing it after.
How to use it
Enter your launch date and click "Start with this template". The whole plan opens as an editable timeline (a Gantt chart), laid out backward from that date. No sign-up, no login. Drag and drop to match your own launch.
The member list comes preloaded with a product manager, engineering, marketing and support, so you can assign each task right away. Share the plan with a link to keep everyone aligned on the way to launch day.