About this template
A new product usually has a launch window before it has a plan. The work between today and that date crosses several teams, and each one waits on a decision from another.
This template lays out development as an editable timeline that starts from your launch date, about 24 weeks from research to launch.
It assumes one physical product. The durations are guidelines. If parts have long lead times, or the product needs certification or regulated labeling, give production setup and quality checks more time, and find out what is required at the very start.
How the plan is broken down
Decide what to make. Research, a concept and a business case, ending with an approval.
Build it and test it. Design, a prototype, then testing and iteration. The design freeze is a task of its own. A change after it means redoing production setup.
Make it and get ready to sell it. Suppliers and tooling, packaging and manuals, quality checks and the first shipment. Sales and marketing prep runs in parallel.
Why the durations are set this way
- Prototype and testing get about six weeks. Building it shows problems the drawings did not. The plan does not assume one round is enough.
- Production setup gets 38 days. Supplier lead times do not shrink because your date is close.
- Quality checks get two weeks. That is the time to inspect the first units before anything ships.
- 4 days between first shipment and launch. Room for stock to arrive where it is sold.
Common pitfalls
- The design keeps changing. A change after the freeze can make ordered parts useless. Fix the freeze date early.
- Costing comes last. "Can we make it" and "can we sell it at that price" are different questions. Cost it while you prototype.
- Sales hears about it just before launch. Product copy and photos take time. Start when the design is frozen.
Who finishes what before the next step starts
Development usually stalls where nobody is sure whose turn it is. For each step, decide who finishes it and what "done" means before you start.
| Step | Who finishes it | Done when |
|---|---|---|
| Concept & business case | Product manager | Who it is for and what problem it solves fit on one page |
| Concept approval | Product manager | Approval is given, with a budget and a launch window |
| Design & specifications | Engineering | The drawings and specs are enough to build a prototype |
| Prototype testing & iteration | Engineering | Every test item has been checked and the fixes are in |
| Costing & pricing | Product manager | The unit cost is known and the price is set |
| Design freeze | Engineering | "We build this" is decided and handed to manufacturing |
| Production setup | Manufacturing | Suppliers and tooling are ready and a start date is set |
| Quality checks | Manufacturing | The first units have been inspected and passed |
| Sales & marketing prep | Sales & marketing | Product copy, photos and the sales channel are ready |
If "done" is written as "explore" or "work on", nobody can say whether it happened. Write it as something that either happened or did not: "decided", "handed over".
If prototype testing runs long, what happens to the launch date
In this plan, a delay reaches the launch along one path:
Prototype testing & iteration → Design freeze → Production setup → Quality checks → First shipment → Launch
Testing is planned from day 76 to day 96. The slack on this path is 4 days after quality checks and 4 days after the first shipment, 8 days in total.
If testing runs a week long, the slack absorbs it and the launch date holds. If it runs two weeks long, the launch moves by 6 days.
Packaging and sales prep can keep moving, unless the design changes a great deal.
If the launch date cannot move, win the time back in this order:
- Narrow what you fix now. Separate "must fix" from "fix in the next version".
- Order long-lead parts first. Some parts can be decided before the design freeze.
- Do not cut quality checks. What you skip here is found by customers.
To keep testing from running long, settle three things before you start: what you test, what counts as a pass, and who decides.
How to use it
Enter your launch date and click "Start with this template". The whole plan opens as an editable timeline (a Gantt chart), laid out backward from that date. No sign-up, no login. Drag and drop to match your own project.
The member list comes preloaded with a product manager, engineering, manufacturing and sales & marketing, so you can assign each step right away. Share the plan with a link so every team follows the same schedule.