[{"data":1,"prerenderedAt":410},["ShallowReactive",2],{"doc:\u002Fgantt\u002Ftemplates\u002Frestaurant-opening":3},{"doc":4,"missing":403},{"id":5,"title":6,"body":7,"category":318,"description":319,"extension":320,"locale":321,"meta":322,"navigation":323,"order":324,"path":325,"seo":326,"stem":342,"summary":343,"template":344,"__hash__":402},"ganttTemplates\u002Fgantt\u002Ftemplates\u002Frestaurant-opening.md","How Long Does It Take to Open a Restaurant? A Lease-to-Grand-Opening Timeline (Free)",{"type":8,"value":9,"toc":306},"minimark",[10,15,19,22,25,29,40,46,52,56,96,100,121,125,128,245,248,252,255,258,261,264,267,270,290,293,296,300,303],[11,12,14],"h2",{"id":13},"about-this-template","About this template",[16,17,18],"p",{},"You have picked a date to open. What is less clear is how the lease, the permits, the build-out and the staff fit into the months before it.",[16,20,21],{},"A restaurant opening is a chain of approvals. In many places, the health department wants to review your plans before construction starts, the building and fire officials inspect when it ends, and you cannot serve the public until the final inspections are passed. Each step waits on the one before it. This template lays the whole process out as an editable timeline, worked backward from your grand opening date, about six months from concept to opening day.",[16,23,24],{},"It assumes a small restaurant in a leased space that needs a build-out. The durations are guidelines. A space that was already a restaurant can be much faster, a bare shell much slower. Which permits you need, how long each takes and when to apply depend on your city, county and state, so the first real task is to ask your local offices and write it down.",[11,26,28],{"id":27},"how-the-plan-is-broken-down","How the plan is broken down",[16,30,31,35,36,39],{},[32,33,34],"strong",{},"Decide what you need before you sign."," Concept, budget and location come first, and the permit list comes before the lease. ",[32,37,38],{},"A space that cannot meet health, zoning or fire requirements is a lease you cannot use."," Ask before you sign, not after.",[16,41,42,45],{},[32,43,44],{},"Design, then get approval, then build."," Drawings go to the health department for plan review and to the building department for a permit before construction starts. Changes are cheap on paper and expensive in a finished kitchen. Menu, suppliers and hiring run alongside.",[16,47,48,51],{},[32,49,50],{},"Pass the inspections, then practice."," Final building, fire and health inspections come before you can open, along with the health department's permit to operate and, where your city requires one, a certificate of occupancy. Training and a soft opening come after that, so the first real service is not the first time the team runs the room.",[11,53,55],{"id":54},"why-the-durations-are-set-this-way","Why the durations are set this way",[57,58,59,66,72,78,84,90],"ul",{},[60,61,62,65],"li",{},[32,63,64],{},"Permit list before the lease, 15 days."," Health, building, fire and liquor are often separate offices. Find out what each needs and how long it usually takes.",[60,67,68,71],{},[32,69,70],{},"The liquor license starts right after the lease."," It is often the slowest item, and in some places licenses are limited in number or tied to the address. Ask your state or local licensing office early. This plan gives it 90 days, which may be far too short or more than you need.",[60,73,74,77],{},[32,75,76],{},"Plan review and the building permit get 20 days together."," Treat this as a placeholder. Health departments we checked in November 2026 publish first-review times from about 7 to 30 business days, before any resubmittals (for example, McHenry County, Illinois and Wayne County, Michigan), and the building permit runs on its own clock. Ask both offices for their current times and stretch this task to match.",[60,79,80,83],{},[32,81,82],{},"Build-out gets 48 days."," Replace this with your contractor's schedule. It is the step that moves most.",[60,85,86,89],{},[32,87,88],{},"10 days for final inspections."," Inspections are booked with each office, and anything that fails has to be fixed and re-inspected.",[60,91,92,95],{},[32,93,94],{},"12 days of training and a 4-day soft opening."," Mistakes are cheaper in front of friends and invited guests than on opening day.",[11,97,99],{"id":98},"common-pitfalls","Common pitfalls",[101,102,103,109,115],"ol",{},[60,104,105,108],{},[32,106,107],{},"Signing the lease first."," The space may not allow the use, or may need work you did not budget for. Turning a space into a restaurant can count as a change of use, which in many cities means a new certificate of occupancy.",[60,110,111,114],{},[32,112,113],{},"Starting construction before plan approval."," Work done before approval may have to be torn out and redone.",[60,116,117,120],{},[32,118,119],{},"Announcing the date too early."," Wait until the final inspection dates are set before you print the date anywhere.",[11,122,124],{"id":123},"who-finishes-what-before-the-next-step-starts","Who finishes what before the next step starts",[16,126,127],{},"An opening stalls where it is unclear whose turn it is. For each step, decide who finishes it and what \"done\" means before you start.",[129,130,131,147],"table",{},[132,133,134],"thead",{},[135,136,137,141,144],"tr",{},[138,139,140],"th",{},"Step",[138,142,143],{},"Who finishes it",[138,145,146],{},"Done when",[148,149,150,162,172,182,193,203,214,224,235],"tbody",{},[135,151,152,156,159],{},[153,154,155],"td",{},"Concept, budget & funding",[153,157,158],{},"Owner",[153,160,161],{},"The concept, seat count and budget ceiling are on one page",[135,163,164,167,169],{},[153,165,166],{},"List permits & licenses",[153,168,158],{},[153,170,171],{},"Every permit is listed with its office, timing and order",[135,173,174,177,179],{},[153,175,176],{},"Sign the lease",[153,178,158],{},[153,180,181],{},"The space is checked against that list and the lease is signed",[135,183,184,187,190],{},[153,185,186],{},"Design & drawings",[153,188,189],{},"Designer",[153,191,192],{},"Drawings are ready to submit for plan review",[135,194,195,198,200],{},[153,196,197],{},"Health plan review & building permit",[153,199,158],{},[153,201,202],{},"Plan approval and the building permit are in hand",[135,204,205,208,211],{},[153,206,207],{},"Build-out & equipment install",[153,209,210],{},"Contractor",[153,212,213],{},"The work is finished and matches the approved plans",[135,215,216,219,221],{},[153,217,218],{},"Final inspections, health permit & certificate of occupancy",[153,220,158],{},[153,222,223],{},"Every final inspection is passed and the health permit and any certificate of occupancy are in hand",[135,225,226,229,232],{},[153,227,228],{},"Menu, pricing & suppliers",[153,230,231],{},"General manager",[153,233,234],{},"The menu is priced and every supplier has a first delivery date",[135,236,237,240,242],{},[153,238,239],{},"Staff training & mock service",[153,241,231],{},[153,243,244],{},"The whole team has run one full service from open to close",[16,246,247],{},"If \"done\" is written as \"work on\" or \"follow up\", nobody can say whether it happened. Write it as something that either happened or did not: \"signed\", \"passed\".",[11,249,251],{"id":250},"if-the-build-out-runs-late-what-happens-to-opening-day","If the build-out runs late, what happens to opening day",[16,253,254],{},"In this plan, a delay reaches opening day along one path:",[16,256,257],{},"Sign the lease → Design → Plan review & permit → Build-out → Final inspections → Training → Soft opening → Grand opening",[16,259,260],{},"The build-out is planned from day 100 to day 148, and the grand opening is day 180. The slack on this path is 2 days before inspections, 2 days before the soft opening and 2 days before the grand opening, 6 days in total.",[16,262,263],{},"If the build-out runs a week long, opening day moves by 1 day. If it runs two weeks long, opening day moves by 8 days. Inspection dates depend on each office's calendar, so when the finish date moves, rebook them the same day.",[16,265,266],{},"Menu, hiring and marketing do not wait on the build-out, so they keep going.",[16,268,269],{},"If opening day cannot move, win the time back in this order:",[101,271,272,278,284],{},[60,273,274,277],{},[32,275,276],{},"Train before the space is ready."," The menu, recipes and service steps can be taught elsewhere. Keep only the full run-through for the restaurant itself.",[60,279,280,283],{},[32,281,282],{},"Shorten the soft opening."," Two nights instead of four still lets the team run the room once.",[60,285,286,289],{},[32,287,288],{},"Do not skip inspections or training."," You cannot open without the approvals, and cutting training hands the cost to your first guests.",[16,291,292],{},"If you cannot win it back, move the date before it goes on flyers and social posts. Changing a date nobody has seen costs little. Changing one you have announced costs trust.",[16,294,295],{},"To keep the build-out from running late, settle three things before it starts: the contractor's finish date, the inspection lead times, and who approves extra work.",[11,297,299],{"id":298},"how-to-use-it","How to use it",[16,301,302],{},"Enter your grand opening date and click \"Start with this template\". The whole plan opens as an editable timeline (a Gantt chart), laid out backward from that date. No sign-up, no login. Add the permits from your list as tasks and drag them to the timing your local offices give you.",[16,304,305],{},"The member list has Owner, General manager, Designer and Contractor, so you can see whose turn each step is. Share the plan by link with your contractor and your team so everyone works from the same dates.",{"title":307,"searchDepth":308,"depth":309,"links":310},"",2,3,[311,312,313,314,315,316,317],{"id":13,"depth":308,"text":14},{"id":27,"depth":308,"text":28},{"id":54,"depth":308,"text":55},{"id":98,"depth":308,"text":99},{"id":123,"depth":308,"text":124},{"id":250,"depth":308,"text":251},{"id":298,"depth":308,"text":299},"business","A free restaurant opening timeline that works backward from your grand opening: concept and funding, the location, permits and licenses, the lease, design and plan review, build-out, final inspections, hiring, training and a soft opening. No sign-up required.","md","en",{},true,31,"\u002Fgantt\u002Ftemplates\u002Frestaurant-opening",{"persona":327,"target-query":328,"sub-queries":329,"avoid-queries":333,"vocabulary":337,"title":6,"description":319},"Someone opening a restaurant, cafe or bar, or a new location of one, who has a target opening date but not a clear order for the lease, permits, build-out and staff","restaurant opening timeline",[330,331,332],"restaurant opening timeline template","how long does it take to open a restaurant","grand opening timeline",[334,335,336],"restaurant opening checklist","new restaurant openings near me","how much does it cost to open a restaurant",[338,339,340,341],"build-out","plan review","certificate of occupancy","soft opening","gantt\u002Ftemplates\u002Frestaurant-opening","About six months from concept to grand opening, with permits and inspections in the right order.",{"version":345,"name":346,"anchor-day":347,"date-label":348,"members":349,"tasks":350},1,"Restaurant Opening",180,"Grand opening date",[158,231,189,210],[351,354,358,363,366,370,372,374,376,379,382,385,388,390,393,397,399],{"name":155,"start":352,"duration":353},0,20,{"name":355,"start":356,"duration":357},"Find a location",10,40,{"name":359,"start":360,"duration":361,"color":362},"List permits & licenses with your city and county",30,15,"#F44336",{"name":176,"start":364,"duration":365,"color":362},50,5,{"name":367,"start":368,"duration":369},"Liquor license application (if serving alcohol)",55,90,{"name":186,"start":368,"duration":371},25,{"name":228,"start":373,"duration":364},60,{"name":197,"start":375,"duration":353,"color":362},80,{"name":207,"start":377,"duration":378},100,48,{"name":380,"start":381,"duration":360},"Hire staff",115,{"name":383,"start":384,"duration":373},"Marketing & grand opening announcement",120,{"name":386,"start":387,"duration":361},"POS, reservations & smallwares",145,{"name":218,"start":389,"duration":356,"color":362},150,{"name":239,"start":391,"duration":392},160,12,{"name":394,"start":395,"duration":396},"Soft opening",174,4,{"name":398,"start":347,"duration":345,"color":362},"Grand opening",{"name":400,"start":401,"duration":360},"Review the first month",181,"FIcSAOUIIiu0p3BLcsknHfI0AkeV3F_xv0etPXSsk5E",[404,405,406,407,408,409],"de","es","fr","pt-br","ja","zh-tw",1795617797162]